About Ashfall
Hubbard Rhino Barn Construction Gallery
-
Soil testing began in late November 2007.
-
Soil testing in November 2008.
-
Excavation of footing trenches began in June 2008.
-
Excavation of footing trench for the north wall of the new rhino barn.
-
Excavation for the footings was done by hand instead of heavy equipment so new fossil finds would not be damaged. Digging continued through June 2008.
-
Excavating waterhole sand below the volcanic ash.
-
Footing pads on side walls are 6 feet by 9 feet and 6 to 9 feet deep.
-
The upper 2-3 feet is volcanic ash, the lower bedding is waterhole sand.
-
University of Nebraska State Museum Vertebrate Paleontologist Mike Voorhies prepares a field jacket near a fossil burrow.
-
Abundant fossils from scavenged skeletons were encountered in the west trench.
-
The pit crew.
-
Ben holds an Oreodont jaw found in waterhole sand.
-
Mike outlines a horse rib.
-
Field jackets protect ash fossils in the west trench.
-
A partial skeleton and skull of a rare raccoon dog and first snake skeleton were major finds in late summer 2008.
-
Preparing for construction of the new rhino barn.
-
Mike Voorhies oversees late summer activity.
-
After a summer of digging, footings are formed for the new foundation.
-
A small excavator assisted with lime hardened sandstone.
-
A Ready Mix pump truck fills footings and pads.
-
A temporary roof will protect the fossil bed while the original rhino barn is dismantled.
-
A temporary roof will protect the fossil bed while the original rhino barn is dismantled.
-
Rick Otto works on a temporary roof that will protect the fossil bed during construction.
-
A view of the construction.
-
The former Rhino Barn is dismantled.
-
The former Rhino Barn is dismantled.
-
The former Rhino Barn is dismantled.
-
The former Rhino Barn is dismantled.
-
The former Rhino Barn is dismantled.
-
A view of the new structure.